Private pilot project · Osubi service area

Osubi Independent Solar Power Pilot

A standalone, privately developed solar-plus-storage mini-grid pilot with its own distribution network, prepaid metering and commercial structure. This module is the live commercial, technical and financial model — change any assumption and every downstream figure recalculates.

Planning Assumption — Subject to Site Survey, Load Assessment, Engineering Design and Supplier Confirmation.
Scenario · basePhase 21.0 MWp2.05 MWh755 customers

Pilot command centre

Every figure below is produced live by the model from the current assumption set. Change any assumption and the whole module recalculates.

PV capacity
1.00
MWp
1,430 modules
Inverter / PCS
1.00
MW AC
DC:AC 1.00
Battery
2.048
MWh
1.8 h at rated AC
Net generation
1.30 GWh
CF 14.8%
Energy sold
1.18 GWh
Delivery 44%
Connections
755
5 anchor
CAPEX
$1.48m
$1.48/W · $2k/conn.
Annual OPEX
$151k
10.2% of CAPEX
Blended tariff
₦544
/kWh
$0.340/kWh · residential ₦209 · commercial ₦618
Capital recovery
6.2 yrs
then 13.8 yrs of regeneration
EBITDA (yr 1)
$236k
Collection 95%
Project IRR
15.9%
NPV $176k @ 14%
Equity IRR
17.3%
Payback 6.2 yrs
LCOE
₦756
/kWh
$0.473/kWh
Min DSCR
2.06
Debt 40% @ 12%
Peak demand
726
kW
Load factor 42%
Renewable share
90%
Curtailment 5%
Readiness score
52
/100
6 of 9 gates met
Land requirement
1.60
ha
5 km 11 kV · 7 km LV

Phase 2 — Full initial Osubi pilot

Cumulative build-out to the full mixed commercial and residential service area.

Low case
$1.60m
Central
$1.75m
High case
$1.90m
1.0 MWp solar PV1.0 MW Deye inverter / PCS capacity2.048 MWh battery storage5 km-radius overhead distribution network6–8 transformers700–900 smart-metered customersFull mixed commercial and residential service area

Engineering & commercial checks

Automatic validation of the current configuration.

  • Storage autonomy of 2.5 h at diversified peak load is below the 3 h minimum for evening peak cover.
  • Usable storage cannot serve the modelled nighttime load.

Planning Assumption — Subject to Site Survey, Load Assessment, Engineering Design and Supplier Confirmation.