Government View · MORE Agenda
Electrification & Delivery
Track electrification status, energy deficit, priority communities, budget scenarios and the state-wide project pipeline.
Grid access (state)
59
%
Target · 2035
95
%
Energy deficit
38
%
Priority LGAs
6
< 40% access
Priority communities
LGAs with lowest electricity access — first for mini-grid & PV deployment.
- Burutu28%
- Ndokwa East30%
- Bomadi32%
- Patani34%
- Warri North44%
Budget scenarios
State + partner capital required to close the access gap.
Conservative
Grid + rooftop, 60% → 75% access by 2030
$220m
2025 – 2030
Balanced (recommended)
Grid + utility PV + mini-grids, 60% → 88%
$480m
2025 – 2032
Accelerated
Full rollout, 60% → 98% access by 2035
$860m
2025 – 2035
Implementation roadmap
Phased rollout across 2025 – 2035
2025
Osubi flagship COD
2026
5 mini-grids online
2028
50 MW state portfolio
2030
150 MW · 80% access
2035
500 MW · 95%+ access
Osubi 15 MW PV + BESS
FinancingOkpe · 15 MW
40% complete
Warri C&I rooftop cluster
FeasibilityWarri South · 8 MW
22% complete
Ndokwa mini-grid programme
DesignNdokwa East · 3 MW
55% complete
Asaba government campus PV
ConstructionOshimili South · 5 MW
78% complete
Ughelli grid-tied utility PV
ConceptUghelli North · 25 MW
10% complete
Burutu riverine hybrid
DesignBurutu · 2 MW
45% complete